NextSource Materials Inc. (TSX:NEXT) (OTCQB:NSRCF) ("NextSource" or "the Company") is pleased to announce the results of a Preliminary Economic Assessment ("PEA") for an enhanced Phase 2 expansion of its 100%-owned Molo Graphite Mine Project in southern Madagascar.
The PEA considered an enhanced Phase 2 expansion consisting of a stand-alone processing plant with a production capacity of 150,000 tonnes per annum ("tpa") of flake graphite concentrate over a 26-year life of mine ("LOM"). The PEA projects that the capital costs to construct 150,000 tpa of processing capacity would be US$155.8 million with a pre-tax NPV utilizing an 8% discount rate of US$929.6 million and a pre-tax IRR of 41.1%.
The PEA assumed the Phase 2 processing plant will be built adjacent to the 17,000 tpa Phase 1 processing plant, currently under construction.
Craig Scherba, P.Geo., President and CEO of NextSource commented,
"We are very pleased the PEA defines the strong financial returns of a larger scale operation and significant scalability of our project as market demand for flake graphite for use in electric vehicle batteries is rising. A Phase 2 expansion of this magnitude will position NextSource as a major global supplier and will underpin our vertical integration strategy to construct our own battery anode facility in due course, enabling direct supply to the electric vehicle battery market."
The PEA was prepared by Erudite Strategies Ltd. ("Erudite") of South Africa, an independent engineering and consulting firm specializing in the mining and processing of commodities and battery materials.
The Company cautions that the PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. Mineral resources are not mineral reserves and do not have demonstrated economic viability and there is no certainty that the PEA will be realized.
PEA RESULTS SUMMARY
The following summary highlights the financial metrics provided in the PEA:
Description | Preliminary Economic Assessment (150k tpa) |
---|---|
Economic Highlights | |
Pre-tax Net Present Value ("NPV") (8% discount rate) (1)(2) | US$929.6 million |
Post-tax and royalty NPV (8% discount rate) (1)(2)(3) | US$612.6 million |
Pre-tax Internal Rate of Return ("IRR") (1)(2)(3)(4) | 41.1% |
Post-tax and royalty IRR (1)(2)(3)(4) | 32.0% |
Life of Mine ("LOM") | 26 years |
Annual average production of SuperFlake® graphite concentrate(5)(6) | 150,000 tonnes |
Payback (Pre-tax) (1)(2)(3)(4) | 3.1 years |
Payback (Post-tax and royalty) (1)(2)(3)(4) | 3.7 years |
Capital cost ("Capex") (including a contingency of $31.96 million) | US$155.8 million |
Operating Costs FOB ("Opex") (per tonne of concentrate following ramp-up) (7) | US$479.03 |
Average sale price of SuperFlake® concentrate (US$/tonne) (8) | US$1,231 |
Operational Highlights | |
Average material mined per annum over LOM | 2,532,345 |
Average Head Grade | 6.16% |
Concentrate purity (Cg) of finished product | 97% |
Average Stripping ratio over LOM | 0.8:1 |
Average carbon recovery | 88.30% |
(1) Assumes Project is financed with 100% equity. Unless otherwise noted, all monetary figures presented throughout this press release are expressed in US dollars (USD).
(2) CAPEX includes process equipment, civil & infrastructure, mining, buildings, electrical infrastructure, project & construction services. Values shown are based on real graphite sales pricing.
(3) Assumes 5% revenue and 1.5% NSR royalty payments.
(4) Assumes no inflationary adjustments in sales price or operating costs.
(5) Assumes all mineralized material from the Company's 2019 Feasibility Study, including ore from the Measured, Indicated and Inferred Mineral Resource categories, are sent to the treatment plant.
(6) Assumes a cut-off grade of 4.5% carbon has been applied, with all material below this cut-off grade treated as waste.
(7) Assumes all concentrate will be sold on a FOB basis at the Port of Ehoala, Madagascar.
(8) Assumes a 2% increase in the sales price reported in the Company's 2019 Feasibility Study (i.e. $1208/tonne), based on current market prices provided by UK-based commodity price reporting agencies Benchmark Minerals Intelligence and Fastmarkets.
CAPEX SUMMARY
Estimate Summary | Cost | % |
---|---|---|
Mechanical equipment | US$24.0 million | 15% |
Structural steel | US$2.6 million | 2% |
Piping and valves | US$2.1 million | 1% |
Freight and transport | US$6.6 million | 4% |
Electrical and instrumentation | US$7.9 million | 5% |
Sub-total supply items | US$43.2 million | 28% |
Engineering and management | US$14.4 million | 9% |
Civil construction | US$24.5 million | 16% |
Infrastructure | US$36.2 million | 23% |
Mechanical erection | US$0.1 million | 0% |
Preliminary and general | US$4.7 million | 3% |
Electrical erection | US$0.8 million | 0% |
Sub-total non-supply items | US$80.7 million | 52% |
Contingency | US$32.0 million | 21% |
Total Estimated CAPEX | US$155.8 million | 100% |
OPEX SUMMARY
Based on discussions with off takers, their preference is to purchase Molo graphite concentrate at the local Madagascar port at freight on board (FOB) China prices. As such, Operating costs ("OPEX") include the all-in FOB cost to ship the graphite concentrate to the local port of Ehoala.
Estimate Summary | Cost |
---|---|
Mining (US$/tonne) | $145.88 |
Processing (US$/tonne) | $190.15 |
Transport to Port of Fort Dauphin (US$/tonne) | $133.00 |
General and admin (US$/tonne) | $10.00 |
Total OPEX | $479.03 |
MINERAL RESOURCES
The Molo project hosts the following mineral resources and remains open along strike and to depth:
Classification | Material Type | Tonnes | %C (Carbon) | Graphite (Tonnes) |
---|---|---|---|---|
Measured | "Low Grade" | 13 048 373 | 4.64 | 605 082 |
Measured | "High Grade" | 10 573 137 | 8.4 | 887 835 |
Total Measured | 23 621 510 | 6.32 | 1 492 916 | |
Indicated | "Low Grade" | 39 539 403 | 4.73 | 1 871 075 |
Indicated | "High Grade" | 37 206 550 | 7.86 | 2 925 266 |
Total Indicated | 76 745 953 | 6.25 | 4 796 341 | |
Measured + Indicated | "Low Grade" | 52 587 776 | 4.71 | 2 476 157 |
Measured + Indicated | "High Grade" | 47 779 687 | 7.98 | 3 813 101 |
Total Measured + Indicated | 100 367 464 | 6.27 | 6 289 257 | |
Inferred | "Low Grade" | 24 233 267 | 4.46 | 1 080 677 |
Inferred | "High Grade" | 16 681 453 | 7.70 | 1 285 039 |
Total Inferred | 40 914 721 | 5.78 | 2 365 716 |
C% = carbon percentage ; Graphite Tonnes = tonnes of graphite concentrate
(1) Mineral Resources are classified according to the Canadian Institute of Mining definitions.
(2) Mineral Resources are reported Inclusive of Mineral Reserves.
(3) "Low Grade" Resources are stated at a cut-off grade of 2% C.
(4) "High grade" Resources are stated at a cut-off grade of 4% C.
(5) Eastern and Western high-grade assays are capped at 15% C.
(6) A relative density of 2.36 tonnes per cubic metre (t/m3) was assigned to the mineralized zones for the mineral resource tonnage estimation.
(7) The effective date of the Mineral Resource tabulation above is August 14, 2014.
(8) Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
METALLURGY & PRICING
The PEA is based on a full suite of metallurgical test work performed by SGS Canada Metallurgical Services Inc. in Lakefield, Ontario, Canada. These tests included lab and bench scale process development work, a bulk sample/pilot plant program, and metallurgical variability testing. The overall graphitic carbon recovery into the final concentrate is 88.3%.
Metallurgical Data - Flake Size Distribution and Product Grade
Product Size | % Distribution | Product Grade (% Carbon) |
+48 mesh (jumbo flake) | 23.6 | 96.9 |
+65 mesh (coarse flake) | 14.6 | 97.1 |
+80 mesh (large flake) | 8.2 | 97.0 |
+100 mesh (medium flake) | 6.9 | 97.2 |
+150 mesh (medium flake) | 15.5 | 97.3 |
+200 mesh (small flake) | 10.1 | 98.1 |
-200 mesh (fine flake) | 21.1 | 97.5 |
Pricing Matrix - Flake Size Distribution Grouping and Product Grade
Product Size | % Distribution | Product Grade (% Carbon) |
>50 mesh | 23.6 | 96.9 |
-50 to +80 mesh | 22.7 | 97.1 |
-80 to +100 mesh | 6.9 | 97.2 |
-100 mesh | 46.8 | 97.6 |
The selling price used in the PEA is the volume weighted average sales price for the various flake sizes and grades of SuperFlake® graphite concentrate that are expected to be produced from the Molo deposit. Prices used are based on current market prices provided by UK-based, commodity price reporting agencies Benchmark Minerals Intelligence and Fastmarkets, who are recognized as leaders in providing independent and unbiased market research, pricing trends and demand and supply analyses for the natural flake graphite market.
No price escalation for graphite sales prices into the future was applied to the PEA model. Current market prices were used and flatlined over the life of mine. No pricing premium for valued-added applications was applied on any sales. Furthermore, no financial or operational calculations and/or scenarios in the PEA financial model with regards to downstream value-added processing of SuperFlake® graphite concentrate were included. This includes purification, spherodization coating for battery-grade graphite and thermal expansion for specialty graphite applications, such as foils.
Battery Anode Facility
The PEA's enhanced Phase 2 capacity was determined based on discussions with automotive manufacturers ("OEMs") and our battery anode offtake partners. The Company and the battery anode offtake partners are evaluating construction of a battery anode facility ("BAF"), capable of converting flake graphite concentrate from any qualified mine into spheronized and purified graphite ("SPG") and into coated SPG ("CSPG"). CSPG is the final form of natural graphite required to manufacture lithium-ion batteries required by OEMs. As announced on November 15th, 2021, the Company initiated a technical study to determine the capital and operating costs for our first BAF and is considering several proposed locations.
Based on recent discussions with OEMs and our battery anode offtake partners, the Company expects demand for CSPG to experience significant growth. For example, a single mid-sized OEM's 7-year demand forecast would require NextSource to construct a BAF with a CSPG production capacity of 58,000 tpa. Since it takes 2.2 tonnes of flake graphite to produce 1 tonne of CSPG, the majority of Phase 2 production capacity would be dedicated to supply the BAF for such a single mid-sized OEM.
Molo PHASE 1 Construction and Commissioning Update
On January 11, 2022, the Company announced the Molo Phase 1 processing plant (the "Processing Plant"), which was fully fabricated and constructed at an offshore facility, had successfully passed Factory Acceptance Testing and final verification. The Processing Plant has since been dismantled, packaged and is now ready to be shipped to the mine site.
Due to Madagascar's ongoing COVID-19 travel restrictions, and recent cyclone activity impacting the eastern seaboard of the country, the commencement of earthworks and civil work at the mine site has been delayed and commissioning of the Molo Phase 1 process plant is now targeted for Q3, 2022.
Phase 1 of the Molo Graphite Mine is fully funded and when commissioned, Molo will become one of the few operating graphite mines outside of China.
The Company has not yet made a production decision in respect of Phase 2. The Company expects that it will assess the results of a definitive feasibility study before making a production decision in respect of Phase 2.
TECHNICAL REPORT FILING
This PEA technical report will be filed under the Company's profile on SEDAR at www.sedar.com and will be posted on NextSource's website at www.nextsourcematerials.com within 45 days of this new release.
Data verification programs have included review of QA/QC data, re-sampling and sample analysis programs, and database verification. Validation checks were performed on data, and comprise checks on surveys, collar co-ordinates and assay data. Sufficient verification checks were undertaken on the database to provide confidence that the database is appropriate to support the technical information contained herein.
QUALIFIED PERSONS
The PEA was prepared in accordance with National Instrument 43-101 standards by Mr. Johann de Bruin, Pr. Eng, of Erudite Strategies. Mr. de Bruin is the Qualified Person who verified the technical data using industry acceptable standards and signed off on the relevant sections in the report to be filed on SEDAR.
Mr. Craig Scherba, P.Geo., President and CEO of NextSource, is the qualified person who reviewed and approved the technical information provided in this press release.
ABOUT NEXTSOURCE MATERIALS INC.
NextSource Materials Inc. is a strategic materials development company based in Toronto, Canada that is intent on becoming a fully integrated, global supplier of critical battery and technology materials needed to power the sustainable energy revolution.
The Company's Molo graphite project in Madagascar is one of the largest known and highest-quality graphite deposits globally, and the only one with SuperFlake® graphite. Construction of Phase 1 of the Molo Project is underway, with commissioning expected in Q3, 2022.
NextSource Materials is listed on the Toronto Stock Exchange (TSX) under the symbol "NEXT" and on the OTCQB under the symbol "NSRCF".
To learn more, please visit the Company's website at www.nextsourcematerials.com or email investor relations at This email address is being protected from spambots. You need JavaScript enabled to view it.
For further information contact: +1.416.364.4911
Brent Nykoliation, Executive Vice President, Corporate Development at This email address is being protected from spambots. You need JavaScript enabled to view it. or Craig Scherba, President and CEO at This email address is being protected from spambots. You need JavaScript enabled to view it.
Safe Harbour
This press release contains statements that may constitute "forward-looking information" or "forward-looking statements" within the meaning of applicable Canadian and United States securities legislation. Readers are cautioned not to place undue reliance on forward-looking information or statements. Forward looking statements and information are frequently characterized by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "potential", "possible" and other similar words, or statements that certain events or conditions "may", "will", "could", or "should" occur. Forward-looking statements include any statements regarding, among others; regarding the results of the PEA for Phase 2 expansion, collaboration agreements to build a value-added CSPG (anode) facility, time to commissioning the Molo Phase 1 and the BAF, the demand for EVs, demand for CSPG, the use of SuperFlake®, successful and on-budget construction of the Molo Graphite Project, CSPG plant and BAF, sourcing the funds needed to construct the BAF, , estimated future production, capex and opex from the Molo Graphite Project (for Phase 1 and Phase 2), completion of the study relating to the BAF, and the continuation of the supply relationships of the Partners. These statements are based on current expectations, estimates and assumptions that involve a number of risks, which could cause actual results to vary and, in some instances, to differ materially from those anticipated by the Company and described in the forward-looking statements contained in this press release. No assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur or, if any of them do so, what benefits the Company will derive there from. The forward-looking statements contained in this news release are made as at the date of this news release and the Company does not undertake any obligation to update publicly or to revise any of the forward-looking statements, whether as a result of new information, future events or otherwise, except as may be required by applicable securities laws. Although the forward-looking statements contained in this news release are based on what management believes are reasonable assumptions, the Company cannot assure investors that actual results will be consistent with them. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the Company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.
Last Trade: | US$0.38 |
Daily Volume: | 0 |
Market Cap: | US$59.200M |
October 24, 2024 October 11, 2024 August 07, 2024 April 10, 2024 |
Northstar Clean Technologies is a cleantech company focused on the sustainable recovery and reprocessing of asphalt shingles. Northstar’s mission is to be the leader in the recovery and reprocessing of asphalt shingles in North America...
CLICK TO LEARN MOREElse Nutrition is changing the face of early childhood nutrition with clean, sustainable, plant-based products. The company has developed the world’s first whole plant-based infant formula that is targeting the $100+ billion global...
CLICK TO LEARN MORECOPYRIGHT ©2022 GREEN STOCK NEWS